Development Name :- May Tree Close
Location :- BB10 2PN, Burnley
Cost of Build :- £3.1m
Programme Start Date :- November 2019
Completion Date :- March 2021
Programme Length :- 17 months
Number of Units :- 17
Units Split :- 9x 2 bed houses, 8x 3 bed houses
Work began in November 2019 on the affordable housing development in Harle Syke, consisting of 9x 2bed houses and 8x 3bed houses, each with a large rear turfed garden and dedicated driveway with electric car charging port installed.
Despite unexpected site closures in 2020 due to COVID restrictions and severe weather issues, the project was completed in March 2021, coming in under the original CSA budget.