Station Road / Calder Green

Development Name :- Station Road

Cost of Build :- £2.7 million

Programme Start Date :- January 2020

Completion Date :- January 2021

Programme Length :- 12 months

Number of Units :- 22

Units Split :- 1 bungalow and 10nr 2 Bedrooms and 11nr 3 Bedrooms

Station Road began in January 2019 and was completed in January 2020 as part of a £2.7m project. This project is part of a 4 year plan to build 436 new homes across East Lancashire.

The project consists of 10nr 2bedrooms  and 11nr 3 bedroom shared ownership homes. Each property has their own back garden with a patio area also.  At the front of each property is a drive for at least 1 vehicle with a planting area and lawn.