Lancaster Refurbishment

Development Name :- Lancaster refurbishment

Cost of Build :- £737,042.00

Programme Start Date :- November 2019

Completion Date :- June 2020

Programme Length :- 7 months

Number of Units :- 20 rooms

Units Split :- 15 bedrooms, 5 self-contained flats


This project involved the full refurbishment of a disused building, turning it into a facility consisting of 15 bedrooms, 5 self contained flats, a communal living area, kitchen and outdoor area.

Work began in November 2019 and was completed in June 2020 as part of an initial £941,000.00 project. Despite barriers faced by the COVID-19 pandemic, the build was handed over on time in June 2020 and came in under cost at £737,042. 00.